Development Progress – Q1 Build Update
Q1 2025 Development Progress: Strong Momentum Across the Board
As we move through the first quarter of 2025, we’re pleased to report significant progress across all of our live development sites. From Longbridge to Cambridge, and from Reading to Manchester, each project is advancing steadily through its build programme, with completions on track and investor confidence strong.Cooper Gate: Delivered and Let
Cooper Gate in Longbridge stands out as a recent success story — not only because of its prime position within a £700 million regeneration zone, but because of the strength of collaboration behind it. From initial off-plan sales through to full tenancy, our partnership with St. Modwen Homes has exemplified what can be achieved through clear communication, trusted relationships, and a shared commitment to quality. The development sold out ahead of schedule, and we’re proud to report that all units are now fully let, with rental values performing exactly in line with forecasts. Cooper Gate is now a thriving community and a tangible result of the Miller Rose approach.Emerald Court, Digbeth – Completion Due Q1 2026
Momentum is building at Emerald Court in Digbeth. Groundworks are now complete, with piling and main drainage fully installed. Ground beam rebar is currently being laid, and steel frame installation is scheduled for May and June 2025. The project remains on track for completion in Q1 2026.Osborne Yard, Manchester – Completion Due Q4 2025
Osborne Yard is progressing rapidly. Concrete has been poured across all levels, and key M&E works are well underway. Intumescent painting is nearing completion, scaffolding is being installed across elevations, and drainage connection works are in progress following a planned road closure. The build remains firmly on schedule.The Hale, Cambridge – Completion Due Q4 2025
In Cambridge, The Hale Apartments continue to progress smoothly. Foundation works are now complete and first lift brickwork is underway. All construction activity is tracking against the agreed programme with no delays or changes. Key milestones will be shared as the year unfolds.RG1, Reading – Completion Due Q4 2025
At RG1 in Reading, strip-out works begin at the end of March and will take around seven weeks. This marks the beginning of the internal redevelopment phase, with full internal construction scheduled to follow. The site remains firmly on track.Supporting Your Investment Every Step of the Way
Mortgages
We work with a trusted network of mortgage brokers who specialise in investment lending, including international and expat buyers. From pre-approval through to completion, our partners offer tailored guidance, competitive rates, and a streamlined process to help investors secure the right finance with confidence.Furnishings
Through our furniture partners, we offer stylish, ready-made furniture packs designed specifically for rental properties. From space planning to installation, each package is curated to maximise appeal, durability, and rental return — ensuring apartments are tenant-ready from the moment keys are handed over.Lettings
Our carefully selected lettings and rental partner ensures every investment is professionally marketed, efficiently let, and expertly looked after. With a focus on tenant quality and long-term value, we minimise void periods and maintain strong rental performance, giving investors peace of mind from day one.Looking Ahead
From structural progress to final fix preparations, we’re proud of the positive momentum across our portfolio. Our focus remains on delivering high-quality homes on time, and on supporting our investors with end-to-end solutions that maximise returns. If you’d like to discuss your next investment, or need support with finance, lettings or furnishing, we’re here to help — just get in touch."*" indicates required fields